Friday, 21 June 2013

Uganda grants tender for biggest power dam to China's Sinohydro Group



By Charles Kazooba
Uganda has signed a contract granting China's Sinohydro Group Ltd. a tender to build a large hydropower dam on the Nile River at a price of $1.65 billion,  reviving a project stalled for years by a lack of money.
Construction of the 600-megawatt Karuma dam in the east African country is expected to start about two weeks after the signing of the contract.
China, which provided credit worth $500 million to help pay for construction of the Karuma dam, has rapidly expanded its investment in infrastructure all over the sub-Saharan Africa.
The project will cost $1.65 billion and will entail both developing the dam and a transmission line to evacuate the power from the generation site to the distribution network.
At the signing ceremony, Synohydro was represented by the company's Chairman, Mr. Zhang Yunli while the government was represented by the Attorney General, Peter Nyombi and Energy Minister, Irene Muloni.
Uganda is banking on Karuma to generate cheap, sufficient power to meet fast-growing energy needs and support an economy eyeing double-digit growth rates once crude oil production starts as anticipated in 2017.
The deal comes after President Museveni held talks with China’s President Xi Jinping, in Durban, South Africa, during the BRICS (Brazil, Russia, India, China and South Africa) summit early this year. The two agreed to quickly come up with a solution for Karuma dam construction, after the procurement process for a contractor had been mired in endless controversy.
Earlier, Three Gorges Corporation, which fronted China International Water and Electric Corporation, appeared to have won the bid to build the Karuma dam. However, several battles in and out of court ensued, with bidding companies accusing each other of flouting procurement rules.
In November 2012, High Court judge Eldad Mwangusya ruled that the bids should be re-evaluated after a successful application for judicial review by one of the bidders, Salini SpA. The firm claimed it had been unfairly dropped from the bidding process as the ministry favoured two firms, CWE (Chinese) and Iran’s Perlite Construction Corporation.
Later on, the Inspector General of Government also intervened and stopped the award of the contract until all the procurement rules had been followed. The government now appears to have sidestepped all this by engaging in a bilateral arrangement with the Chinese government to expedite the project. Sinohydro will build the dam at a cost of $1.65bn. 